Results 1 to 2 of 2

Thread: Engineering Consulting/Custom Capital Equipment Design & Manufacturing

  1. #1
    DCOOK87
    Guest

    Engineering Consulting/Custom Capital Equipment Design & Manufacturing

    []
    Last edited by DCOOK87; 11-17-2014 at 05:09 PM.

  2. #2
    Technical Fellow Kelly_Bramble's Avatar
    Join Date
    Feb 2011
    Location
    Bold Springs, GA
    Posts
    2,611
    The long version on how to estimate man-hours and then costing is in my book:

    "Engineering Design for Manufacturability".

    The short, forum post version is to break the work required down into tasks and man hours required for the tasks then assign your cost rate.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •